About the project

This was a rehabilitation project where sections of a 100-year-old structure, Elan Valley Aqueduct (EVA), needed to be replaced. The EVA is an extremely crucial resource as it supplies water to Birmingham and its adjacent areas. There was a need to refurbish and modernize the aqueduct so that it can be preserved for the future. For this, a new conduit with a tunnel of 1.8 km long and 3.0 m diameter was proposed to be constructed. To construct the bypass conduit, a horizontal working platform was required to support the construction traffic, the 1000 ton crane used to assemble the Tunnel Boring Machine (TBM), and finally, the 150 ton TBM.

The solution consisted of a reinforced soil wall using StrataGrid™ 120 and 60 and site-won cohesive material as part of the cut-and-fill balance of the project.

 

On top of the reinforced soil wall, a reinforced working platform was constructed with selected granular material of 970 mm thickness and biaxial geogrid to distribute the load.

The use of StrataGrid™ helped in considerable cost savings compared to the conventional method of constructing the wall. It was an environment-friendly solution.

image-1
image-2
image-3

CONSULTATION

From know-how to manufacture, installation and support.

Strata not only provides geotechnical products, but our team of 200+ engineers can help you with your turnkey project by supplying you with technical knowhow and support as to how our products can help you finish your projects in time while keeping costs down.

Send us your queries and we will get back to you with our expertise.

More success stories

Loop reinforced soil wall at Trichy

Loop reinforced soil wall at Trichy

The Design and Construction of the Reinforced Soil Wall (RS wall) in the Four Laning of Trichy section of NH-227, under the Bharatmala Pariyojana initiative, posed complex challenges that necessitated innovative solutions from Strata.

Read more
No concrete. Leaner pavement. Improved load bearing capacity.

No concrete. Leaner pavement. Improved load bearing capacity.

In any project, constructing on a weak subgrade is always a challenge. In this project, our client was confronted with a similar problem at their proposed container terminal in Kolkata, one of the four metro cities.

Read more
Protection for wind turbine generator footings for Erosion control

Protection for wind turbine generator footings for Erosion control

Owing to soil erosion because of wind and rainwater run-off, Suzlon was plagued with the exposure of foundations for its twenty wind energy generators (WTGs) at Mandsaur, Madhya Pradesh. Soil erosion can be severe during heavy rain or wind, and footings founded at shallow depths can get exposed. StrataWeb® geocells laid at the surface with appropriate in-fill protect against such erosion.

Read more