logo
project-banner
LOCATION

Mancherial- Repallewada, Telangana

CLIENT

HG Infra Projects Engineering LTD.

PRODUCT USED

APPLICATION

Design and construction of RS Wall with StrataWall™ EC system

About the project

Strata undertook a significant project involving the design and construction of Reinforced Soil (RS) wall approaches along the NH-363 highway, spanning a 42-kilometer stretch from Mancherial to Repallewada in Telangana.

The client’s primary requirement was to find a cost-effective and efficient alternative to the conventional approach of using Reinforced Cement Concrete (RCC) retaining walls along the highway approaches. This was motivated by the acknowledgment that RCC retaining walls are not only costlier but also time-consuming compared to the potential benefits offered by Reinforced Soil walls.

In addressing the challenges posed by traditional RS wall systems, Strata introduced groundbreaking solutions, notably the development and implementation of the Embedded Connection (EC) system. This innovative system seamlessly connects the proprietary StrataStrip™ with facing panels in geosynthetic reinforced soil retaining walls, eliminating the need for exposed steel components that are susceptible to corrosion. This not only enhances the safety of the structure by avoiding potential connection failures due to corrosion but also contributes to the overall ease of construction.

The project successfully utilised two types of backfill (soil and pond ash), and Strata’s proposal to incorporate non-woven geotextile between the soil fill and drainage media prevented the migration of fines, ensuring long-term stability. Strata’s holistic approach, from planning and design to timely execution, provided a turn-key solution for the approach walls, demonstrating their commitment to delivering comprehensive and efficient solutions.

Strata’s proactive role in coordinating with the client, coupled with regular site monitoring from both on-site and head office perspectives, ensured smooth progress throughout the project. The StrataWall™ EC system’s unique features, such as embedded SCN and SCW connectors in the panel during casting, not only facilitated a safer and corrosion-resistant connection but also contributed to increased overall construction efficiency. In summary, Strata’s innovative solutions not only overcame the challenges associated with conventional methods but also provided a turnkey, cost-effective, and safer solution for the successful construction of RS wall approaches along the NH-363 highway in Telangana.

image-1

CONSULTATION

From know-how to manufacture, installation and support.

Strata not only provides geotechnical products, but our team of 200+ engineers can help you with your turnkey project by supplying you with technical knowhow and support as to how our products can help you finish your projects in time while keeping costs down.

Send us your queries and we will get back to you with our expertise.

More success stories

StrataWeb® geocells – A slope erosion protection system for embankments

StrataWeb® geocells – A slope erosion protection system for embankments

The Jordan Ministry of Energy and Mineral Resources (MEMR) was planning to build a petroleum strategic reserves terminal in the east of Amman, Jordan. They wanted to increase the petroleum storage capacity in the area, which required an increase in the base width of the embankment. The slopes of the embankment required protection from slope erosion.

Read more
Slope protection of partial wall on flyover using StrataWeb® geocells

Slope protection of partial wall on flyover using StrataWeb® geocells

The ramps of the grade separators are constructed either as embankments with natural slopes or as reinforced soil walls. In the case of partial walls, where sloped embankments are supported on reinforced soil walls, the embankment slopes needed to be given adequate protection against soil erosion, which could otherwise damage the fascia of the underlying reinforced soil wall and also induce seepage into the system. The slopes of the embankments were of the order of 30° with the horizontal. The reinforced soil walls supporting the embankments were as high as 10 m. The heights of the embankments were of the order of 5 m.

Read more
Rehabilitation of road in the busy city town centre in Karnataka

Rehabilitation of road in the busy city town centre in Karnataka

Monsoons in North Karnataka are notorious for damage to roads. The site was plagued with problems like reflective cracks, potholes, undulating surfaces etc., resulting in slow traffic movement and heavy vehicular damage. This stretch had to be rehabilitated time and again over the past several years, and no solution was proving to be long-term. Since the area is a major commercial hub, it was impossible to close off this section for an extended period completely, so a quick but long-term solution was needed.

Read more